15. Implementation
Table 3 outlines the implementation of recovery actions specified in this plan for the period of five years. DEC is responsible for the implementation of the Recovery Plan.
| Action | Action Title | Priority | Estimated Cost/year ($) | Total Cost ($) | Responsible Party | In-Kind ($) | Cash ($) | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | |||||||
| 1.1 | Undertake surveys and threat assessment at known populations and those areas likely to contain Grevillea beadleana. | 1 | $8,000 | $16,000 | $8,000 | $8,000 | $8,000 | $48,000 | DEC | $40,000 | $8,000 |
| 1.2 | Inform all relevant land managers of Grevillea beadleana locations and hold discussions to protect all populations. | 1 | $400 | $400 | $800 | DEC | $800 | ||||
| 1.3 | Assess known Grevillea beadleana sites to determine whether declaration as Critical Habitat within the meaning of the TSC Act is warranted. | 1 | $400 | $400 | $400 | $400 | $400 | $2,000 | DEC | $2,000 | |
| 2.1 | Continue population studies into Grevillea beadleana at all known sites. | 1 | A | A | A | A | A | - | DEC | $0 | |
| 2.2 | Continue research into the seedbank and fire ecology of Grevillea beadleana. | 1 | $5,000 | $5,000 | $5,000 | $15,000 | DEC | -$0 | $15,000 | ||
| 2.3 | Develop appropriate management strategies and make recommendations about the need for further research programs following a review of actions 2.1 and 2.2. | 2 | $2,000 | $2,000 | DEC | $2,000 | |||||
| 2.4 | Prepare and implement a Grevillea beadleana ex-situ conservation program and conduct a re-introduction feasibility study. | 2 | $2,000 | $2,000 | DEC | $2,000 | |||||
| 3.1 | Investigate options for protecting Grevillea beadleana populations on private and leasehold land. | 1 | $2,000 | $2,000 | $2,000 | $6,000 | DEC | $6,000 | |||
| 3.2 | Undertake discussions with landowners and lessees about the protection of Grevillea beadleana populations on private and leasehold land. | 1 | $2,000 | $2,000 | $2,000 | $2,000 | $2,000 | $10,000 | DEC | $10,000 | |
| 4.1 | Reduce or eliminate the threat of frequent fire regimes to Grevillea beadleana by implementing appropriate planning mechanisms. | 1 | $5,000 | $5,000 | $5,000 | $5,000 | $5,000 | $25,000 | DEC | $25,000 | |
| 4.2 | Apply appropriate management strategies to eliminate or reduce site-specific threats identified during population surveys and ecological research. | 2 | $2,000 | $2,000 | $2,000 | $2,000 | $2,000 | $10,000 | DEC | $10,000 | |
| 4.3 | Maintain confidentiality of all Grevillea beadleana locations. | 2 | - | - | - | - | - | - | DEC | $0 | |
| 5 | Prepare and display an information leaflet at relevant District DEC offices and local Councils for interested local landowners. | 2 | $5,000 | $5,000 | DEC | $5,000 | |||||
| 6 | Convene annual Recovery Team meetings to co-ordinate and review the implementation of the actions in this recovery plan. | 1 | $2,000 | $2,000 | $2,000 | $2,000 | $2,000 | $10,000 | DEC | $10,000 | |
| Total | $31,800 | $34,800 | $26,400 | $23,400 | $19,400 | $135,800 | $112,800 | $23,000 | |||
A - undertake concurrently with surveys of known sites in year 1